The Montara Wellhead Platform is approximately 157 km from the Ashmore Reef National Nature Reserve & Cartier Island Marine Reserve.
On 21 August 2009, during drilling operations at the Montara Wellhead Platform an uncontrolled release of oil and gas occurred from the H1 well.
🔥 On 1 November the leaking well was successfully intercepted, however during operations to complete the “well kill”, fire broke out on the West Atlas rig and the Montara Wellhead Platform.
On 3 November 2009, the fire was extinguished.
🕐 For a period of just over 10 weeks in fall 2009, oil and gas continued to flow unabated into the Timor Sea, and patches of sheen or weathered oil could have affected at various times an area as large as 90,000 square kilometres.